Pictures from "Building for God's Glory":

 

 
August 20, 2009 (Family Ministry Center Completed)
Thank you VERY MUCH Lloyd and Dave for the Aerial Photos
 
 
August 19, 2009 (Family Ministry Center progress)
 
 
August 3, 2009 (Family Ministry Center progress)
 
 
August 3, 2009 (Family Ministry Center progress)
 
 
July 28, 2009 (Family Ministry Center progress)
 
 
July 24, 2009 (Family Ministry Center progress)
 
 
July 17, 2009 (Family Ministry Center progress)
 
 
July 13, 2009 (Family Ministry Center progress)
 
 
 
July 8, 2009 (Family Ministry Center progress)
 
 
June 23, 2009 (Family Ministry Center progress)
 
 
June 16, 2009 (Family Ministry Center progress)
 
 
June 10, 2009 (Family Ministry Center progress)
 
 
June 5, 2009 (Family Ministry Center progress)
 
 
May 29, 2009 (Family Ministry Center progress)
 
 
May 9, 2009  (Family Ministry Center progress)
 
 
April 19, 2009 (Family Ministry Center progress)
[Signing names and favorite verses on walls]
 
 
March 28, 2009
 
 
March 17, 2009 (Family Ministry Center progress)
 
 
March 3, 2009 (Family Ministry Center progress)
 
 
Febuary 10, 2009 (Family Ministry Center progress)
 
 
January 7, 2009 (Family Ministry Center progress)
 
 
December 10, 2008 (Family Ministry Center progress)
 
 
December 10, 2008 (Live Nativity set up)
 
 
December 09, 2008 (Live Nativity set up)
 
 
December 08, 2008 (Family Ministry Center progress)
 
 
December 04, 2008 (sidewalks, stairs and new parking lots)
 
 
November 19, 2008 (installing internal wall)
 
 
November 7, 2008
 
 
October 31, 2008
 
 
October 27, 2008 (parking lot work)
 
 
October 23, 2008
 
 
 
October 16, 2008
 
 
October 8, 2008
 
 
 
October 1, 2008 and a couple from last week.
 
 
September 18, 2008 - Parking lot work!
 
 
September 15, 2008
 
 
September 10, 2008
 
 
September 9, 2008
 
 
 
September 3, 2008
 
 
Roof is placed! August  20, 2008
 
 
July 28, 2008
 
 
 
Continuing to Pray - July 13, 2008
 
 
July 12, 2008
 
 
 
June 20, 2008
 
 
 
June 5, 2008
 
 
 
May 2008
 
 
May 9, 2008
 
 
 
April 30, 2008
 
 
April 25, 2008
 
 
April 20, 2008  
 
 
March 31, 2008
 
 
 
March 27, 2008 - Roof trusses going up!
 
 
March 26, 2008 - Still hard at work!

 
March 24, 2008 - First day steel is going up!!!
 
 
March 1, 2008 - OUR FAMILY AT WORK!
 
 
 
February 29, 2008 - laying water supply line
 
 
 
February 18, 2008 - Pipeline photos
 
 
Our foundation being poured!
 
 
Pre-Slab Panarama of our site! Thanks Dave!
 
 
Concrete poured for the footings
 
 
Setting the forms for the foundation.
 
 
Foundation footings and plumbing trenches are dug.
 
 
Excavation Begins!
 
  
Our crew hard at work preparing to move the Portable.

 
 
Delivery of our steel!
 

 
The proposed building!
North Elevation South Elevation
East Elevation West Elevation
Proposed Building Location